Question
A can complete a piece of work in 10 days. B in 15 days
and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed (in days)?Solution
Work done by ( A + C ) in 2 days = 2 (1/10 + 1/20 ) = 2 ((2 + 1)/20 ) = 6/20 = 3/10 Remaining work = 1 - 3/10 = 7/10 ( B + C )’s 1 day’s work = 1/15 + 1/20 = (4 + 3)/60 = 7/60 Time taken by ( B + C ) to finish 7/10 part of the work = 60/7 × 7/10 = 6 days Total time = 2 + 6 = 8 days Alternate method: Let total work = LCM (10,15,20) = 60 units So A’s 1 day work = 60/10 = 6 units B’s 1 day work = 60/15 = 4 units C’s 1 day work = 60/20 = 3 units A & C’s work for 2 days = (6+3)×2 = 18 units So remaining work = 60 – 18 = 42 units Now A is replaced by B So B & C together will do work in 1 day = 3 + 4 = 7 units So they can do the remaining job in = 42/ 7 = 6 days So total days = 6 + 2 = 8 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
‘X’ and ‘Y’ can do a task together in 15 days. If ‘X’ alone takes 25 days to complete it, then how much time will ‘Y’ take to finish the...
‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?