Question
A can complete a piece of work in 10 days. B in 15 days
and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed (in days)?Solution
Work done by ( A + C ) in 2 days = 2 (1/10 + 1/20 ) = 2 ((2 + 1)/20 ) = 6/20 = 3/10 Remaining work = 1 - 3/10 = 7/10 ( B + C )’s 1 day’s work = 1/15 + 1/20 = (4 + 3)/60 = 7/60 Time taken by ( B + C ) to finish 7/10 part of the work = 60/7 × 7/10 = 6 days Total time = 2 + 6 = 8 days Alternate method: Let total work = LCM (10,15,20) = 60 units So A’s 1 day work = 60/10 = 6 units B’s 1 day work = 60/15 = 4 units C’s 1 day work = 60/20 = 3 units A & C’s work for 2 days = (6+3)×2 = 18 units So remaining work = 60 – 18 = 42 units Now A is replaced by B So B & C together will do work in 1 day = 3 + 4 = 7 units So they can do the remaining job in = 42/ 7 = 6 days So total days = 6 + 2 = 8 days
निम्नलिखित में कौन-सा शब्द पुल्लिंग है ?
जिसका कोई निश्चित निवास-स्थान न हो '' के लिए एक शब्द होग�...
'दूसरों से आगे बढ़ने की इच्छा' के लिए एक शब्द क्या होगा?
इनमें से 'तत्सम' शब्द कौन-सा है?
‘ रामकृष्णाचार्य’ शब्द में समास का प्रकार है:
कार्य को नए ढंग से करने की पद्धति
शीतल को कोई नौकरी पानी है। इसमें कोई नौकरी विशेषण की �...
पर्यायवाची की दृष्टि से एक वर्ग शुद्ध
रिक्त स्थान के लिए उपयुक्त शब्द क्या होगा?
मैंने अपने भ�...
गिरीश का संधिविच्छेद क्या होगा ?