Question
A can complete a piece of work in 10 days. B in 15 days
and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed (in days)?Solution
Work done by ( A + C ) in 2 days = 2 (1/10 + 1/20 ) = 2 ((2 + 1)/20 ) = 6/20 = 3/10 Remaining work = 1 - 3/10 = 7/10 ( B + C )’s 1 day’s work = 1/15 + 1/20 = (4 + 3)/60 = 7/60 Time taken by ( B + C ) to finish 7/10 part of the work = 60/7 × 7/10 = 6 days Total time = 2 + 6 = 8 days Alternate method: Let total work = LCM (10,15,20) = 60 units So A’s 1 day work = 60/10 = 6 units B’s 1 day work = 60/15 = 4 units C’s 1 day work = 60/20 = 3 units A & C’s work for 2 days = (6+3)×2 = 18 units So remaining work = 60 – 18 = 42 units Now A is replaced by B So B & C together will do work in 1 day = 3 + 4 = 7 units So they can do the remaining job in = 42/ 7 = 6 days So total days = 6 + 2 = 8 days
Which of the following statements is correct?
How many persons are designated between U and the one who works as PO?
How many persons visits after the one who visits Afghanistan?
- Six boxes (S, T, U, V, W, and X) are kept one above another such that the bottommost box is numbered as 1 and the topmost box is numbered as 6 but not nece...
What is the direction of flat of Z with respect to flat of P?
Who among the following is wife of Prashant?
Which of the following box is kept immediately below box B?
What is the difference of ages of C and B?
What is the date of booking for H?
Answer the questions based on the information given below.
Seven persons stay in 7 different floors of a building such that no two persons stay...