Question
A can complete a piece of work in 10 days. B in 15 days
and C in 20 days. A and C worked together for two days and then A was replaced by B. In how many days, altogether, was the work completed (in days)?Solution
Work done by ( A + C ) in 2 days = 2 (1/10 + 1/20 ) = 2 ((2 + 1)/20 ) = 6/20 = 3/10 Remaining work = 1 - 3/10 = 7/10 ( B + C )’s 1 day’s work = 1/15 + 1/20 = (4 + 3)/60 = 7/60 Time taken by ( B + C ) to finish 7/10 part of the work = 60/7 × 7/10 = 6 days Total time = 2 + 6 = 8 days Alternate method: Let total work = LCM (10,15,20) = 60 units So A’s 1 day work = 60/10 = 6 units B’s 1 day work = 60/15 = 4 units C’s 1 day work = 60/20 = 3 units A & C’s work for 2 days = (6+3)×2 = 18 units So remaining work = 60 – 18 = 42 units Now A is replaced by B So B & C together will do work in 1 day = 3 + 4 = 7 units So they can do the remaining job in = 42/ 7 = 6 days So total days = 6 + 2 = 8 days
What is the color of Methyl Orange in an acidic medium?
Which noble gas is utilized in radiotherapy?
The function of quick lime in soda lime mixture is to
What is the atomicity of Helium?
What is the chemical name of quick lime?
Which statement about carbon credits is incorrect?
What is the primary component in silver-colored paints?
Which of the following rock is not sedimentary rock?
Manganite is an ore/mineral of -
Which substance is also known as 'Oil of Vitriol'?