Question
The efficiency of A, B, C, D are in the ratio of 6 : 5 :
4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to complete the same work?Solution
Efficiency of (A+C) = (6+4) = 10 Days taken by (A+C) together to complete the work = 6 days Efficiency of (B+D) = (5+3) = 8 So, B and D will take time = (Total days of (A+C)รTotal Efficiency of (A+C))/(Total Efficiency of (B+D)) = (6 ร10)/8 = 60/8 = 7(1/2) days
What was the final score difference between Lando Norris and Max Verstappen in the 2025 Formula 1 World Championship standings?
Which of the following was the fourth unicorn to join the state-run Open Network for Digital Commerce (ONDC)?
NABARD is working towards helping the farmers tackling the adverse impact climate change.For this purpose it has collaborated with __________ and Bill a...
- What is the name of the AI-powered virtual home loan advisor launched by L&T Finance?
What is the effective date for the higher D - SIB buffer requirements for State Bank of India ( SBI ) and HDFC Bank?
Which bankโs recent (Nov 2024) integration with Swift GPI benefit customers making international money transfers?
In which year the Sarang Helicopter Display Team of India was formed?
What does the National Youth Day commemorate and when is it celebrated?
The new CPI-AL/RL series covers how many states and union territories?
What is the primary focus of the Memorandum of Understanding (MoU) signed between India and the European Union regarding semiconductors?