Question

    The efficiency of A, B, C, D are in the ratio of 6 : 5 :

    4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to complete the same work?
    A 7(1/2) days Correct Answer Incorrect Answer
    B 8(1/3) days Correct Answer Incorrect Answer
    C 10 days Correct Answer Incorrect Answer
    D 8 days Correct Answer Incorrect Answer

    Solution

    Efficiency of (A+C) = (6+4) = 10 Days taken by (A+C) together to complete the work = 6 days Efficiency of (B+D) = (5+3) = 8 So, B and D will take time = (Total days of (A+C)×Total Efficiency of (A+C))/(Total Efficiency of (B+D)) = (6 ×10)/8 = 60/8 = 7(1/2) days