Question
A can complete a work in 20 days and B can complete it in 30 days. They work together for 6 days, then B leaves. In how many total days will the work be completed?
More Time and work Questions
- A and B together can do a piece of work in 15 days which B and C together can do in 20 days. After A has been working at it for 3 days and then by B for 11...
- Two friends, Aman and Vivek started a project together. They worked together for the first 6 days, but only 30% of the project was completed. Therefore, bo...
- A and B can complete a piece of work in 15 days and 10 days respectively. They started the work together, but B left after some days and A finished the rem...
- A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio of the ef...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 18 days. 'A' started the work alone and worked on...
- 16 men or 24 women can complete a piece of work in 36 days. A man and a woman together complete the work and receive a total wage of Rs. 9,600. Find the di...
- A person can complete a work in 15 days, and another person can complete the same work in 20 days. They work together for 5 days, and then the first person...
- 'X' and 'Y' together can complete the work in 16 days. 'Y' alone can complete the work in 24 days. If Z is 50% more efficient than X, find the time taken b...
- Ganga, Yamuna &Saraswati can complete a piece of work in 30, 40 & 60 days respectively. All 3 of them started working together and after 4 days, Ganga quit...
- 33 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 33 ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)