Question
Aβ and βBβ together can complete a work in 20 days
while βAβ takes 30 days to complete the same work alone. If βCβ is 60% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 60 units Efficiency of (A + B) = 60/20 = 3 units/day Efficiency of βAβ = 60/30 = 2 unit/day Therefore, efficiency of βBβ = 3 β 2 = 1 units/day Efficiency of βCβ = 1.6 Γ 1 = 1.6 units/day Required time taken = 60/1.6 = 37.5 days
Which data analytics technique is suitable for handling missing data points in a dataset?
The dynamic memory allocation is the memory allocation done at the _________.
Which of these can be overloaded?
Which of the following is a valid token in lexical analysis?
What does a "Shared Lock" in a DBMS locking protocol allow?
Β
Consider a 4-way set associative cache consisting of 128 lines with a line size of 64 words. The CPU generates a 20-bit address of a word in main memor...
In dynamic programming, what is memoization?
What is the minimum no. of variables/ features required to perform clustering?
What is the basic component of an electronic circuit that restricts the flow of current?
When designing a sequential circuit, what is the purpose of flip-flops or latches?