Question
Aβ and βBβ together can complete a work in 20 days
while βAβ takes 30 days to complete the same work alone. If βCβ is 60% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 60 units Efficiency of (A + B) = 60/20 = 3 units/day Efficiency of βAβ = 60/30 = 2 unit/day Therefore, efficiency of βBβ = 3 β 2 = 1 units/day Efficiency of βCβ = 1.6 Γ 1 = 1.6 units/day Required time taken = 60/1.6 = 37.5 days
The Reserve Bank has given its approval to SBI Mutual Fund (SBI MF) for acquiring up to 9.99% of the paid-up share capital or voting rights of which ban...
According to OAG data for December 2025, which airport was ranked as the busiest in the world by seat capacity?
How many Key Performance Indicators (KPIs) are monitored for Aspirational Blocks under Sampoornata Abhiyan 2.0?
Which collective name is given to the group of states including Manipur, Meghalaya, and Tripura?
Which recommendation did the RBIβs Internal Working Group (2025) make regarding the 14-day variable rate repo/reverse repo operations?
What was Indiaβs emphasis during the COP29 negotiations in Baku, Azerbaijan, regarding climate finance?
Which borrower category accounted for approximately 80% of total small business credit, as per the CRIFβSIDBI report?
Which country has become the first to formally recognize the Taliban government in Afghanistan?
Following the reduction in reciprocal tariffs by the United States, Goldman Sachs revised Indiaβs CY26 Real GDP growth forecast to which of the follow...
The Jammu and Kashmir cricket team won its maiden Ranji Trophy title in the 2025β26 season by defeating which team in the final?