Question

    A’ and ‘B’ together can complete a work in 20 days

    while ‘A’ takes 25 days to complete the same work alone. If ‘C’ is 60% more efficient than ‘B’, then find the time taken by ‘C’ alone to complete the whole work.
    A 63.5 days Correct Answer Incorrect Answer
    B 64.5 days Correct Answer Incorrect Answer
    C 60.5 days Correct Answer Incorrect Answer
    D 62.5 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let the total work = 100 units Efficiency of (A + B) = 100/20 = 5 units/day Efficiency of ‘A’ = 100/25 = 4 unit/day Therefore, efficiency of ‘B’ = 5 – 4 = 1 units/day Efficiency of ‘C’ = 1.6 × 1 = 1.6 units/day Required time taken = 100/1.6 = 62.5 days

    Practice Next