Question
'R' can independently complete a task in 36 days, whereas 'S' can accomplish 40% of the same work within 16 days. 'S' starts the task solo and withdraws after 10 days. Subsequently, the remaining work is undertaken collaboratively by 'R' and 'M,' culminating in its completion in 12 days. Calculate the duration required for 'S' and 'M' to jointly execute the same task.
More Time and work Questions
- . If 3 goats or 5 sheep can graze a field in 56 days, then in how many days can 6 goats and 10 sheep graze the same field?
- 'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find...
- 60 men can complete a piece of work in 12 days. 12 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
- A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 60% of the wor...
- ‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 30 hours. If ‘B’ completed the rest of the work in 2...
- Varun and Arnav can finish a work in 28 days and 56 days respectively when working alone. Varun starts first. In how many days should Arnav join him so tha...
- A team of ‘a’ mechanics can finish a repair job in 6 days. But every day exactly 12 mechanics remain absent. Hence, the job is finished in 1/2 more time th...
- Working together, Amit and Pawan can finish a task in 22.5 days, and Pawan and Chirag can complete 60% of the same task in 14.4 days. Given that Amit is 12...
- "A certain sales target can be completed by a team of both men and womens in 60 days. If you replace eight womens with eight men, the same target can be ac...
- 'A' requires 16 more days to finish a task compared to 'B'. When 'A' and 'B' collaborate, they complete the task in 9 days fewer than 'B' would need to fin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)