Question
Person A is twice as efficient as Person B. Person B can
complete a certain task in 32 days, while Person C takes 4 days more than Person A to finish the same task. Which of the following could be the number of days they work together such that the task remains incomplete?Solution
According to the question,
Time taken by βAβ to complete the work = 32/2 = 16 days
Time taken by βCβ to complete the work = 16 + 4 = 20 days
Let the total work = 160 units
Efficiency of βAβ = 160/16 = 10 units/day
Efficiency of βBβ = 160/32 = 5 units/day
Efficiency of βCβ = 160/20 = 8 units/day
When they work together for 7 days, work done = (10 + 5 + 8) Γ 7 = 161 units
Therefore, maximum number of days they can work together such that the work doesnβt get completed is 6 days.
'X' and 'Y' together can complete the work in 16 days. 'Y' alone can complete the work in 24 days. If Z is 50% more efficient than X, find the time tak...
6 men and 10 boys can finish a task in 18 days. If each boy is between 1/3rd to equal the efficiency of a man, find the maximum and minimum number of da...
- If Ankit takes four times the time that Ravi takes or five times the time that Sandeep takes to finish a task, and all three working together can complete ...
'A' alone can do some work in 18 days. 'B' is 20% more efficient than 'A'. 'A' worked alone for 12 days and left. How much time (in days) does 'B' need ...
P and Q individually can complete the work in 22 days and 33 days respectively. If the time taken by R alone to complete the work is 1.25 times the time...
Ajay started a work and left working after 8 days. Vijay finished the remaining work in next 36 days. Had Ajay left the work after working for 12 days t...
Two people, A and B, working separately can sanitize a building in 6 and 10 hours, respectively. They work in stretches of one hour alternately. If A be...
The efficiency of A, B, C, D are in the ratio of 6 : 5 : 4 : 3. If A and C can do a work together in 6 days. Then How much days B and D will take to com...
Anil can do a piece of work in 25 days. He alone worked at it for 10 days and then Sunil completed alone the rest work in 15 days. In how many days, the...
A builder recruited 60 workers to do a task in 90 days. It was discovered that only 1/3 of the task was achieved after 60 days. Determine how many addit...