πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    'A' and 'B' together can do a piece of work in 12 days

    while 'B' and 'C' together can do the same work in 16 days. 'A' started the work alone and worked on it for 1 day, then 'B' alone worked on it for 9 days and 'C' alone completed the remaining work in 18 days. Find the time taken by 'B' alone to complete the whole work.
    A 24 days Correct Answer Incorrect Answer
    B 48 days Correct Answer Incorrect Answer
    C 36 days Correct Answer Incorrect Answer
    D 60 days Correct Answer Incorrect Answer
    E 40 days Correct Answer Incorrect Answer

    Solution

    Let the total work be 48 units. {LCM of 12 and 16} Combined efficiency of 'A' and 'B' = 48 Γ· 12 = 4 units/day Combined efficiency of 'B' and 'C' = 48 Γ· 16 = 3 units/day Amount of work done by 'A' in 1 day = 1 Γ— a units
    Amount of work done by 'B' in 9 days = 9 Γ— b units
    Amount of work done by 'C' in 18 days = 18 Γ— c units We have,
    a + b = 4
    b + c = 3 So, a = 4 βˆ’ b and c = 3 βˆ’ b Total work = 48
    (4 βˆ’ b) + 9b + 18(3 βˆ’ b) = 48
    4 βˆ’ b + 9b + 54 βˆ’ 18b = 48
    58 βˆ’ 10b = 48
    10b = 10
    b = 1 unit/day Time taken by 'B' alone to complete the work = 48 Γ· 1 = 48 days

    Practice Next

    Relevant for Exams:

    ask-question