πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      'A' and 'B' together can do a piece of work in 12 days

      while 'B' and 'C' together can do the same work in 16 days. 'A' started the work alone and worked on it for 1 day, then 'B' alone worked on it for 9 days and 'C' alone completed the remaining work in 18 days. Find the time taken by 'B' alone to complete the whole work.
      A 24 days Correct Answer Incorrect Answer
      B 48 days Correct Answer Incorrect Answer
      C 36 days Correct Answer Incorrect Answer
      D 60 days Correct Answer Incorrect Answer
      E 40 days Correct Answer Incorrect Answer

      Solution

      Let the total work be 48 units. {LCM of 12 and 16} Combined efficiency of 'A' and 'B' = 48 Γ· 12 = 4 units/day Combined efficiency of 'B' and 'C' = 48 Γ· 16 = 3 units/day Amount of work done by 'A' in 1 day = 1 Γ— a units
      Amount of work done by 'B' in 9 days = 9 Γ— b units
      Amount of work done by 'C' in 18 days = 18 Γ— c units We have,
      a + b = 4
      b + c = 3 So, a = 4 βˆ’ b and c = 3 βˆ’ b Total work = 48
      (4 βˆ’ b) + 9b + 18(3 βˆ’ b) = 48
      4 βˆ’ b + 9b + 54 βˆ’ 18b = 48
      58 βˆ’ 10b = 48
      10b = 10
      b = 1 unit/day Time taken by 'B' alone to complete the work = 48 Γ· 1 = 48 days

      Practice Next

      Relevant for Exams:

      ask-question