Question
Aman, Bishnu, and Chintu can each
complete 20%, 25%, and 60% of the work in 4 days, 9 days, and 27 days, respectively. If all three begin the work together but Aman stops after 4 days, how many more days will it take for Bishnu and Chintu to finish the remaining work together?Solution
ATQ
‘Aman’, ‘Bishnu’ and ‘Chintu’ will complete the whole work in 20 days (4/0.20), 36 days (9/0.25) and 45 days (27/0.60) respectively. Let total amount of work = 180 units (LCM of 20, 36 and 45) Amount of work done by ‘Aman’ in one day = 180/20 = 9 units Amount of work done by ‘Bishnu’ in one day = 180/36 = 5 units Amount of work done by ‘Chintu’ in one day = 180/45 = 4 units Amount of work done by ‘Aman’, ‘Bishnu’ and ‘Chintu’ together in 4 days = 4 × (9 + 5 + 4) = 72 units Time taken by ‘Chintu’ and ‘Bishnu’ together to complete the remaining work = (180 – 72)/(5 + 4) = 12 days
A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days wi...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, the...
Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete th...
Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20%...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5...
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the...
- 'Amit', 'Ravi', and 'Neha' can finish a piece of work in 66, 99, and 132 days respectively. They all started the work, but Amit left 8 days before the work...
A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alo...