Question
Aman, Bishnu, and Chintu can each
complete 20%, 25%, and 60% of the work in 4 days, 9 days, and 27 days, respectively. If all three begin the work together but Aman stops after 4 days, how many more days will it take for Bishnu and Chintu to finish the remaining work together?Solution
ATQ
‘Aman’, ‘Bishnu’ and ‘Chintu’ will complete the whole work in 20 days (4/0.20), 36 days (9/0.25) and 45 days (27/0.60) respectively. Let total amount of work = 180 units (LCM of 20, 36 and 45) Amount of work done by ‘Aman’ in one day = 180/20 = 9 units Amount of work done by ‘Bishnu’ in one day = 180/36 = 5 units Amount of work done by ‘Chintu’ in one day = 180/45 = 4 units Amount of work done by ‘Aman’, ‘Bishnu’ and ‘Chintu’ together in 4 days = 4 × (9 + 5 + 4) = 72 units Time taken by ‘Chintu’ and ‘Bishnu’ together to complete the remaining work = (180 – 72)/(5 + 4) = 12 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
‘X’ and ‘Y’ can do a task together in 15 days. If ‘X’ alone takes 25 days to complete it, then how much time will ‘Y’ take to finish the...
‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?