Question
Machine X is 100% more efficient than Machine Y, and
Machine Y is 75% more efficient than Machine Z. Machines X and Z, working together, can complete a certain task in 15 days. How many days will it take for Machines Y and Z, working together, to complete twice the amount of work, if Machine Z operates at only half of its normal efficiency? ΒSolution
Let the efficiency of 'Z' be 4x units/day. So, efficiency of 'Y' = 4x X (7/4) = 7x units/day And, efficiency of 'X' = 14x units/day So, total work = (14x + 4x) X 15 = '270x' units Therefore, required time = (2 X 270x) Γ· (7x + 0.5 X 4x) = (570x/9x) = 60 days
Which artisan from Chhattisgarh received the National Handicrafts Award for 2023?
In which year was the World Bank established?
The Ganga Expressway inaugurated by PM Modi in Hardoi is how many kilometers long?
Which country is ranked first for cyberattacks in 2024, according to the CloudSEK report?
In July, the number of total account holders under the PMJDY reached 495.6 million, with a total outstanding of over Rs 2 trillion. Of this, _______ are...
Under which legislation were the violations by Reliance General Insurance detected during inspection?
In which Indian state is the Pench Tiger Reserve (PTR) located, recently designated as India's first Dark Sky park?
In a significant development, India is believed to have placed a funding request of around_____Β in its first call with the Pandemic Fund of the World ...
Bangladesh became the first South Asian country to join which UN water governance treaty in 2025?
On which date will the President of India attend the SOAR β Skilling for AI Readiness programme?