Question
Aman finishes 2/5 of a task in 8 days, while Bhanu
completes the entire task in 16 days. How long will it take for both Aman and Bhanu, working together, to complete 90% of the task?Solution
ATQ; Time taken by ‘Aman’ to complete whole work alone = 8 × (5/2) = 20 days Let total work = 80 units Efficiency of ‘Aman’ = 80/20 = 4 units/day Efficiency of ‘Bhanu’ = 80/16 = 5 units/day Required time taken = {(0.9 × 80)/(5 + 4)} = 8 days
Select the option that indicates the correct arrangement of the given words in the order in which they appear in the English dictionary.Â
1) Sit...
_____________ was the temporary Chairman of the first meeting of the Constituent Assembly held on 9 December 1946.
Who controls the Janpad Panchayat?
'Beeja' and 'Mala' are the branches of which tribe of Rajasthan?
Which of the following was one of the impact of Swadeshi movement in the communication system of India?
Match the following awards 2019:
(a) Best Translator Award                              1. Pulavar V. Prabhakar...
What is Laissez-faire?
In which year Swami Vivekananda established the Ramakrishna Mission at Belur?
The study of languages ​​is called.Â
which channel is between Andaman and Nicobar Islands?