Question
A, B, and C can complete a task individually in 45, 35,
and 63 days respectively. They start working together, but A leaves 24 days before the work is completed, and B leaves 10 days after A leaves. How many total days does it take to finish the work?Solution
Let total amount of work = 315 units (LCM of 45, 35 and 63)
Amount of work done by A in one day = 315/45 = 7 units
Amount of work done by B in one day = 315/35 = 9 units
Amount of work done by C in one day = 315/63 = 5 units
Let total time taken to complete the whole work is βxβ days
According to question;
5 Γ x + 9 Γ (x β 14) + 7 Γ (x β 24) = 315
Or, 21x = 315 + 168 + 126
Or, 21x = 609
Or, x = 29
Which of the following can be beaten into thin sheets?
Consider the following three nuclear reactions:
Wh...
A body of mass 2 kg is moving in SHM with angular frequency 4 rad/s and amplitude 0.1 m. Max kinetic energy is:
Which of the following is a compound?
1 mole of carbon atoms = ______ g of carbon atoms
Which of the following are the components of aqua β regia?
Which of the following gases is also known as a 'Stranger' gas?
Which of the following statements is not correct about the dual nature of matter?
What happens when dilute hydrochloric acid is added to iron fillings ?
_______ Chromosomes are affected in Turner syndrome.