Question
P and Q together can finish a task in 72 days while Q and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the remaining task in 54 days, in how many days can R complete the whole task working alone?
More Time and work Questions
- ‘X’ and ‘Y’ together can complete a work in 8 days, while ‘Y’ and ‘Z’ together can complete the work in 5 days. If ‘Y’ takes 10 days to complete the work a...
- Two efficient workers or three non-efficient workers can complete a certain task in 20 days. If each efficient worker improves their efficiency by 33(1/3)%...
- A can finish a work in 12 days and B can finish the same work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alon...
- A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?
- Neha and Priya are assigned a piece of work. Neha can complete 8 units of work each day, while Priya can finish the whole task alone in 32 days. If the tot...
- 18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the task...
- Ashish and Anil can do a piece of work in 10 days and 15 days respectively. Ashish completed 40% of the work. Find the time taken by Anil to complete the r...
- A and B together can complete a work in 12 days, B and C together in 15 days, and C and A together in 20 days. In how many days can A, B and C together com...
- A is twice as efficient as B. A and B together can complete a piece of work in 12 days. If B and C together can complete the same work in 18 days, then fin...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)