Question
P and Q together can finish a task in 72 days while Q
and R can do it in 48 days. If P worked for 18 days, Q worked for 30 days, and then R finished the remaining task in 54 days, in how many days can R complete the whole task working alone?Solution
ATQ,
Let the total work = 288 units (LCM of 72 and 48) Work done by P and Q together in one day = 288/72 = 4 units Work done by Q and R together in one day = 288/48 = 6 units Work done by P and Q together in 18 days = 18 × 4 = 72 units ---- (I) Work done by Q and R together in 12 days = 12 × 6 = 72 units ---- (II) Q’s 18 days work and R’s 12 days work have been included in (I) and (II), respectively. Work done by R alone in 42 days = 288 – 72 – 72 = 144 units Work done by R in one day = 144/42 = 24/7 units Time taken by R alone to complete the full work = 288 ÷ (24/7) = 84 days
Recently in Dec 2022, the Ministry of Civil Aviation issues guidelines for PLI incentive scheme to support indigenous ___.
How many aggregators have been successfully enlisted for pursuing the goal of uniting organisations dedicated to promoting ‘Brand India’ by the One ...
- Who won the 2025 Women's Indian Premier League (WPL) Title?
The Reserve Bank of India recently cancelled the license of which cooperative bank in August 2025?Â
In the newly established hydrogen blending project in Ahmedabad, what is the initial percentage of green hydrogen blended with natural gas?
The Rajasthan government announced an investment of how much to develop the Maharana Pratap Tourist Circuit?
What is the estimated total cost of Phase II of the Odisha PVTG Empowerment and Livelihood Improvement Programme (OPELIP)?
- What is a key feature introduced in BHIM 3.0?
In which year was the SAMRIDH scheme, aimed at accelerating startup growth, inaugurated?
What is the objective of SAP’s MoU with Gati Shakti Vishwavidyalaya (GSV)?Â