      Question

      Time taken by 'X', 'Y' and 'Z' to finish a task is 48 days,

      72 days, and 96 days respectively. All started the task together, but 'X' left 12 days before completion and 'Y' left 6 days before completion. Find the total approximate time required to finish the task.
      A 65 days Correct Answer Incorrect Answer
      B 13 days Correct Answer Incorrect Answer
      C 78 days Correct Answer Incorrect Answer
      D 30 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the total work be 288 units (LCM of 48, 72, and 96)

      Efficiency of 'X' = 288 / 48 = 6 units/day

      Efficiency of 'Y' = 288 / 72 = 4 units/day

      Efficiency of 'Z' = 288 / 96 = 3 units/day

      Let the work be completed in 'n' days.

      Then,

      (6 + 4 + 3) Γ— (n - 12) + (4 + 3) Γ— 6 + 3 Γ— 6 = 288

      Or, 13n - 156 + 42 + 18 = 288

      Or, 13n = 384

      So, n = 384 / 13 = 29.54 β‰ˆ 30 days