'P', 'Q', and 'R' can complete a job in 60, 90, and 120
days respectively. They begin together, but 'P' leaves 10 days before the work is done and 'Q' leaves 5 days before completion. How long did the work take? (Calculate approximate value)Solution
ATQ,
Let the total work be 360 units (LCM of 60, 90, 120)
Efficiency of 'P' = 360 / 60 = 6 units/day
Efficiency of 'Q' = 360 / 90 = 4 units/day
Efficiency of 'R' = 360 / 120 = 3 units/day
Let the time taken = n days
(6 + 4 + 3)(n - 10) + (4 + 3)(5) + 3(5) = 360
Or, 13n - 130 + 35 + 15 = 360
Or, 13n = 440
So, n = 440 / 13 = 33.84 ≈ 34 days
Which vaccine was prequalified by the WHO as the first approved shot for Mpox?
The revamped PM SVANidhi scheme has been extended till which year?
- Why did Reliance Consumer Products (RCPL) acquire Velvette?
According to the latest Periodic Labour Force Survey (PLFS), what was India’s unemployment rate in July 2025?
- What is the focus of the AI Kiran initiative launched in India?
What is the target renewable energy capacity for India by 2030?
What major amendment did the Banking Laws (Amendment) Act, 2025 introduce regarding “substantial interest”?
Recently Dr. Srivari Chandrasekhar, Secretary, Department of Science and Technology, inaugurated the 1st ASEAN-India Start-up Festival (AISF) in which ...
- Who won the Women’s Singles title at the 2025 All England Badminton Championships?
- What key observation was made using the Aditya-L1 mission’s VELC instrument?