'P', 'Q', and 'R' can complete a job in 60, 90, and 120
days respectively. They begin together, but 'P' leaves 10 days before the work is done and 'Q' leaves 5 days before completion. How long did the work take? (Calculate approximate value)Solution
ATQ,
Let the total work be 360 units (LCM of 60, 90, 120)
Efficiency of 'P' = 360 / 60 = 6 units/day
Efficiency of 'Q' = 360 / 90 = 4 units/day
Efficiency of 'R' = 360 / 120 = 3 units/day
Let the time taken = n days
(6 + 4 + 3)(n - 10) + (4 + 3)(5) + 3(5) = 360
Or, 13n - 130 + 35 + 15 = 360
Or, 13n = 440
So, n = 440 / 13 = 33.84 ≈ 34 days
Which of the following were the main purpose of the Cabinet Mission?
1. Preparatory discussions with elected representatives to secure agreeme...
On what date did the Bangladesh Liberation War conclude?
In which year did the Battle of Buxar take place?
He developed a spiritual practice called Internal Yoga. One of his close spiritual collaborator, Mirra Alfassa, founded an ashram in his name in Pondic...
Which movement was launched by Mahatma Gandhi in 1942.
In which year was the Third Battle of Panipat fought? Â
Consider the following statements with reference to the organizations before the establishment of Indian national congress:
1. The East India A...
During the Swadeshi Movement, which key figure called it "Bahishkar Yoga"?
Which one of the following pairs is not correctly matched?
Consider the following statements about the Abhinav Bharat Society:
1. It was a secret society founded by Vinayak Damodar Savarkar and his bro...