'P', 'Q', and 'R' can complete a job in 60, 90, and 120
days respectively. They begin together, but 'P' leaves 10 days before the work is done and 'Q' leaves 5 days before completion. How long did the work take? (Calculate approximate value)Solution
ATQ,
Let the total work be 360 units (LCM of 60, 90, 120)
Efficiency of 'P' = 360 / 60 = 6 units/day
Efficiency of 'Q' = 360 / 90 = 4 units/day
Efficiency of 'R' = 360 / 120 = 3 units/day
Let the time taken = n days
(6 + 4 + 3)(n - 10) + (4 + 3)(5) + 3(5) = 360
Or, 13n - 130 + 35 + 15 = 360
Or, 13n = 440
So, n = 440 / 13 = 33.84 β 34 days
Which of the following is the most commonly used communication protocol for sending and receiving email?
Which of the following is not an operating system?
Symbols A-F are used in which one of the following ?
Which of the following is not true about RAM?
Where is the basic input/output system (BIOS) stored?
Slide setup, slide orientation, presentation themes and background in MS-PowerPoint 2016 (MS-PowerPoint 2016) appear under which of the following menu?
What does PIN stands for?
Internet Explorer is a web browsing software developed in the year 1995 by ______.
A_________ is a component of motherboard which absorbs the heat produced by the processor and other components of a computer?
DVD technology uses an optical media to store the digital data. DVD is an acronym for