Question
A can complete a job in 15 days; B in 20 days. They work
together for 5 days. What fraction remains?Solution
ATQ,
In 1 day they do (1/15 + 1/20 = 7/60).
In 5 days = 35/60 = 7/12. Remaining = 1 – 7/12 = 5/12
Approximately what is the Coefficient of Variation of first 50 natural numbers ?
Which of the following is a possible change in total revenue that occurs if you increase the price of a good with unit elasticity?
Which of the following best explains why the J-curve effect occurs?
The velocity of money is
If the money supply grows 5 per cent, and real output grows 2 per cent, prices should rise by
Which method is used by Hicks to eliminate the income effect when price of a product is changed
Commodity X and Y have an equal price elasticity of supply. The supply of X rises from 400 units to 500 units due to a 20 percent rise in its price. Cal...
What is the probability of getting the sum as a prime number if two dice are thrown?
What is the terms of trade formula?
What is the Slope of the Straight line PPC curve between cloth and wheat?