Question
Pawan completes in two days the same amount of work that
Qureshi completes in four days. Pawan alone can finish the entire task in 15 days. How many days will it take for Pawan and Qureshi to complete the entire task if they work together?Solution
ATQ, ‘Pawan’ is twice as efficient as ‘Qureshi’. Let efficiency of ‘Qureshi’ be ‘q’ units per days and efficiency of ‘Pawan’ be ‘p’ units/day Therefore, p = 2q Let ‘Pawan’ and ‘Qureshi’ together takes ‘d’ days to complete the work Therefore, (p × 15) = (p + q) × d Or, 2q × 15 = 3q × d Or, d = 10 days
Who is often referred to as the father of microbiology and observed bacteria and protozoa using microscopes?
Match the following:
1.        Mitochondrion:                              A- Suicidal bag
2. �...
The phenomenon slickenside is found in
When Marginal cost is at lowest, Marginal product will be:
Which gas is typically used in the Totally Chlorine Free (TCF) bleaching method for cotton fiber?
How does the release of root exudates impact the microbial population in the rhizosphere?
Time-Temperature Indicators, Biosensors, Ripeness Indicators and Radio Frequency Identification are some quality indicators which may be used in:
Indicator plant for Permanent Wilting Point
Total Polar Compounds are formed when:
Which of the following element is a part of cytochrome oxidase ?