Question

Ravi and Manish can do a piece of work in 16 days and 20 days respectively. How long will it take to finish the work if Manish is to be replaced by Sanjay after 2 days? Given that Sanjay and Manish can together finish the work in 12 days

A 7.8 days
B 10.1 days
C 8 days
D 9.2 days