Question
'A' alone can do some work in 20 days, 'B' alone can do
the same work in 30 days. If they work on alternate days, starting with 'B', then the work will be finished in:Solution
Let the total work be 60 units {LCM (20 and 30)} So, efficiency of 'A' = 60 ÷ 20 = 3 units/day And efficiency of 'B' = 60 ÷ 30 = 2 units/day Work done in every 2 days (B + A) = 2 + 3 = 5 units So, work done in 24 days by 'A' and 'B' = (24 ÷ 2) x 5 = 60 units Total time taken = 24 days
Choose the true statement from the following statements regarding the Terai region found in the state of Uttarakhand -
I) Artesian wells are foun...
Which Indian men’s hockey player was recently conferred with the prestigious Major Dhyan Chand Khel Ratna Award for his leadership and performance, in...
Maharana Pratap, a contemporary of Akbar, was a ruler of which of the following kingdoms?
Kinetic and potential energies of a body are the components of its ______ energy.
Kautilya in Arthashastra has mentioned _______ sources of law.
Following are the Central Federations of Trade Unions of Workers formed in India:
1. Indian National Trade Union Congress (INTUC)
2. All I...
Match the following musical instruments with the maestros who play them.
DLS Method is sometimes seen in the news . What does the “ S ” stand for in DLS?
Which movie got best film tag on the OTT(over-the-top) platform in the year 2022?
Which of the following is made to heat tetrafluoroethene on high pressure with free radical or percussive catalyst?