Question
A is thrice as good a workman as B and therefore is able to finish a job in 60 days less than
B. Working together, they can do it in:
Solution
Efficiency Ratio A : B = 3 : 1 Time Ratio A : B = 1 : 3 Difference in time units = 3 - 1 = 2 units. Given difference = 60 days. So, 2 units = 60 => 1 unit = 30 days. A takes 30 days (1 unit). B takes 90 days (3 units). Together = (A × B) / (A + B) = (30 × 90) / (30 + 90) = 2700 / 120 = 22.5 days.
More Time and work Questions
- A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C tog...
- A can finish a work in 18 days and B can finish it in 24 days. They work together for 6 days, then A leaves. In how many more days will B finish the remain...
- A fence is constructed using 900 wooden planks. ‘X’ alone can place 10 planks per minute, while ‘Y’ alone can complete the fence in 100 minutes. ‘Z’, a cur...
- 'B' and 'C' in a team can complete a piece of work in 25 days and on other hand 'B' alone can do the same work in 40 days. If they started the work in a t...
- ‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to compl...
- The time taken by P to complete a task is half of the time taken by Q. Q and R working together finish the task in 20 days, while P and R take 15 days. How...
- The efficiency ratio of Neha, Karan, and Ishaan is 16:11:14, respectively. Together, they can complete a task in 30 days. Neha and Karan started the task, ...
- Ram and Shyam are partners in completing a project. Ram can finish the project in 42 days, while Shyam can complete it in 54 days. Both began the project t...
- Akhil and Nikhil together can complete a work in 10 days while Nikhil alone takes 15 days to complete 30% of the work. If the efficiency of Sachin is 25% m...
- 20 men can finish a work in 220 days, but at the end of 90 days, 20 additional men are employed. In how many more days will the work be completed?