      10 men or 50 women can complete a piece of work in 40

      days. A man and a woman together complete the work and receive a total wage of Rs. 6,000. Find the difference between the wages received by them.
      A Rs.4,000 Correct Answer Incorrect Answer
      B Rs.3,600 Correct Answer Incorrect Answer
      C Rs.3,750 Correct Answer Incorrect Answer
      D Rs.3,520 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Let the efficiency of a man and a woman be 'M' and 'W' units/day respectively. We have, 10M Γ— 40 = 50W Γ— 40 So, 10M = 50W Or, (M/W) = (50/10) = 5 Required difference = {(5 - 1) /(5 + 1) } Γ— 6000 = (4/6) Γ— 6000 = Rs. 4,000