Question
A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 70% of the work.
More Time and work Questions
- A team of 'x' boys can complete a job in 18 days if they all work together. However, every day, 15 boys leave the team after starting the task, and it now ...
- A can complete a work in 30 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 60% of the work...
- A ranch has 70 horses, and there’s food to last for 6 days. If 14 more horses are added, then how many days will the food last?
- If a group of 20 boys and 10 girls can finish a task in 50 days, and a team of 8 girls alone can complete the same task in 120 days, how long will it take ...
- A man, a woman, a boy, and a girl can complete a certain task individually in 84 days, 105 days, 140 days, and 210 days respectively. How long will it take...
- P can do a piece of work in 12 days, Q can complete double the work in 20 days and R can do the work in 15 days. If all of them together earn Rs. 2500, the...
- A can copy 70 pages in 20 hours, A and B together can copy 120 pages in 12 hours. Then in how many pages can B copy 10 hours.
- Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both had done the work...
- A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- ‘A’ alone can do some work in 10 days. ‘B’ and ‘C’ together can do the same work in 4 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by...