Question

    A can complete a work in 30 days. B takes 6 days less

    than A to complete the same work. In how many days can both of them together complete 60% of the work together?
    A 8 days Correct Answer Incorrect Answer
    B 6 days Correct Answer Incorrect Answer
    C 10 days Correct Answer Incorrect Answer
    D 12 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Time taken by B to complete the work = 30 – 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.60 x 120/(4+5) = 8 days

    Practice Next