Question
'M' alone finishes a project in 30 days. 'M' and 'N'
together can complete the same project in 16(2/3) days. How many days would 'N' need to do the project alone?Solution
ATQ,
Let 16(2/3) = 50/3 Let the total work be 150 units (LCM of 30 and 50/3) Efficiency of M = 150 ÷ 30 = 5 units/day Combined efficiency of M and N = 150 ÷ (50/3) = 9 units/day So, efficiency of N = 9 - 5 = 4 units/day Therefore, time taken by N = 150 ÷ 4 = 37.5 days
The rural development projects and men behind them are listed below. Which of the following is correctly matched?
1.      Bhoodan Movement...
Which of these green house gas is most abundant in the atmosphere?
What is the end product of the nitrification process in the nitrogen cycle?
 What is the seed rate of hybrid cotton with a spacing of 120 × 60 cm?
The form of education which is confined within the boundaries and follow a set pattern of curriculum is termed as
Which cereal crop is most tolerant to saline and alkali soils
Sand dunes are commonly seen in:
Average capacity of a windmill would be about:
What is conservation agriculture?
A system in which forest trees are grown along with agricultural crops and grasses on the same land at the same time is known as ____