Question
'M' alone finishes a project in 30 days. 'M' and 'N'
together can complete the same project in 16(2/3) days. How many days would 'N' need to do the project alone?Solution
ATQ,
Let 16(2/3) = 50/3 Let the total work be 150 units (LCM of 30 and 50/3) Efficiency of M = 150 ÷ 30 = 5 units/day Combined efficiency of M and N = 150 ÷ (50/3) = 9 units/day So, efficiency of N = 9 - 5 = 4 units/day Therefore, time taken by N = 150 ÷ 4 = 37.5 days
The South Korean won is the official currency of which country?
What percentage of deposits were held by individuals as of September 2024, according to the RBI Quarterly BSR-2 report?
Consider the following statements about ‘Warli painting’:Â
1.   Recently, an exhibition traces the artistic journey of the Mashe family ...
How many AI start-ups are expected to benefit from NVIDIA’s Inception Program under the AP initiative?
Who has been appointed as the new Economic Affairs Secretary effective July 1, 2025?Â
What amount did LIC pay as stipend to Bima Sakhis in FY2024–25?
Which of the following startup of India became 100th unicorn startup?
Who became the second Indian woman to win a gold medal at the World Military Championships?
What is the main purpose of the Deregulation Commission announced by the Indian government?
Where in India the Kisan Bhawan and Beekeepers Conference has been inaugurated?