Question
Mira is 40% more efficient than Priya, and Neha is 10%
more efficient than Mira. If Neha and Mira together can do a piece of work in 15 days, in how many days will Priya complete the same work alone?Solution
ATQ, Let efficiency of Priya be βxβ units per day. Ratio of efficiency of Priya, Mira, and Neha = x: 1.4x: 1.54x = 100:140:154 Let total amount of work = (140 + 154) Γ 15 = 4440 units Time taken by Priya to complete the work = 4440/100 = 44.4 days
As of April 26, 2023, how many cumulative enrolments have been achieved under the Pradhan Mantri Jeevan Jyoti Bima Yojana (PMJJBY)?
What is the minimum transfer limit for Real Time Gross Settlement (RTGS) as of June 2020?
P, Q, R, S, T and U are six friends. Which of the following is/are sufficient to compare heights of S and T?
1. R is shorter than P but taller...
Which one of the following elements has the highest boiling point?
From which country does Brookfield Asset Management Corporation originate, establishing itself as one of the world's largest alternative investment mana...
The Sundarbans delta is formed by the depositional action of the Ganga, Brahmaputra and which of the following rivers?Β
In which type of tax is the marginal tax rate higher than the average tax rate?
Who is known as the father of Civil-Services in India?
What is the height of elevation of the Peninsular plateau?
Siachen in Himalayas is: