Question

A can complete a work in 18 days and B in 24 days. They work together for 4 days, then C (who alone can complete the work in 36 days) joins them. Find the total time to complete the work.

A 9(1/9) days
B 8(8/9) days
C 7(2/9) days
D 3(5/9) days