Question
A work can be completed by ‘A’ and ‘B’, alone in 12 days and 18 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ‘A’, ‘B’ and ‘C’ together can complete the whole work in 4 days.
More Time and work Questions
- Three Typists Axe, Wye and Zed working together 3 hours per day and can type 720 pages in 12 days. In a day Wye types as many pages more than Axe as Zed ty...
- ‘D’ and ‘E’ together can finish a task in 40 days, while ‘E’ and ‘F’ together can finish the same task in 30 days. ‘D’ and ‘E’ together worked on it for 35...
- 'Amit' can finish a __ percentage of work in 4 days on his own. 'Bishnu' requires 4 days less than 'Amit' to complete the same task individually. Consequen...
- Ram can do a piece of work in 12 days and Shyam can do the same work in 16 days. They both started work together, Ram left 2 days before the completion of ...
- P and Q together can do a job in 6 days, Q & R can finish the same work in 60/7 days. P started the work and worked for 3 days. Q & R contin...
- Working in a shift of 5 hours 39 workers take 12 days to build a stretch of highway. In how many days will 30 workers working 6 hours a day, complete the w...
- 'A' and 'B' alone can complete a work in 14 days and 21 days, respectively. Find the time taken by them to complete the work if they work on alternate days...
- Two pipes A and B can fill a tank in 24 min., and 32 min, respectively. If both the pipes are opened simultaneously, after how much time B should be closed...
- 25 men and 45 women can complete a piece of work in 15 days, while 15 men and 60 women can complete it in 20 days. In how many days can 69 men and 67 women...
- ‘R’ and ‘S’ can complete an assignment in 72 days and 90 days respectively while ‘R’, ‘S’ and ‘T’ together can complete the same assignment in 24 days. Fin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt