A work can be completed by βAβ and βBβ, alone in
12 days and 18 days, respectively. Find the number of days taken by βCβ to complete the same work alone if βAβ, βBβ and βCβ together can complete the whole work in 4 days.Solution
Let total work = 36 units (LCM of 12 and 18) Efficiency of βAβ = (36/12) = 3 units/day Efficiency of βBβ = (36/18) = 2 units/day Combined efficiency of βAβ, βBβ and βCβ = (36/4) = 9 units/day Efficiency of βCβ = 9 β (3 + 2) = 4 units/day Required time taken = (36/4) = 9 days
Rice plants prefer absorption of N fertilizer in form of
The groundwater table is measured by:
Which type of cooperative primarily deals with the marketing of agricultural produce?
What is India's share in the world's cotton production?
The mineral source of plant nutrient Boron whose deficiency leads to pollen sterility isΒ
Sodium adsorption ratio is a measure of the amount of sodium (Na) relative to calcium (Ca) and magnesium (Mg) in the water extract. Which of the followi...
Which is not true for Mycorrhizae Fungi?
Lichens, the pioneer organisms that initiate ecological succession are actually a symbiotic association of
Which of the following is NOT a key practice in Natural Farming?
What physical property of soil increases with primary tillage?