Question
Lata can do 1/3rd of a work in 4 days and
Asha can do 1/6th of the same work in 3 days. If both work together then how many days will it take to complete 75% of the work?Solution
Lata does the 1/3rd part of a work in = 4 days In 1 day, Lata will do = 12 Work            Archna does the 1/6th part of a work in = 3 days In 1 day, Archana will do = 18 Work If both work together, efficiency will be 2+3 = 5
In a situation, when a company borrows money to be paid back at a future date with interest, it is known _____.Â
Stand Up India Scheme provide financial aid for Working Capital needs through which organisation?
Consider the following statements about National Housing Bank (NHB):
       I.           It was set up by an Act of Parliamen...
All single payment transactions of Rs. ______ crore and above undertaken by entities (non-individuals) should include remitter and beneficiary LEI info...
YUVIKA Programme will impart basic knowledge on space technology, space science, and space applications, while preference will be given to rural areas. ...
Which of the following best describes the primary purpose of the ASBA process?
Consider the following statements regarding the Priority Sectors Lending:
1. Besides microfinance groups, individual farmers are also eligible to...
Hornbill Festival is celebrated in which State?
The 'Ration Aapke Gram' scheme was recently launched in _____________.
Consider the following about 'Prior Learning Scheme’:
I. It is a skill certification programme implemented by National Skill Development Corpor...