Question

A and B together can complete a task in 40 days, while A alone takes 100 days to finish it. When A, B, and C work together, they can complete the task in 20 days. Approximately how many days will it take for A and C to complete the task working together?

A 40.5 days
B 28.5 days
C 35.5 days
D 50.5 days
E None of these