Question
βPβ is 20% more efficient than βQβ. βPβ can
do a piece of work in 15 days. They begin the work together, but βQβ leaves after 6 days. The rest of the work is completed by βPβ in βxβ days. What is the value of βxβ?Solution
ATQ, Time taken by βQβ to complete the work = 1.2 Γ 15 = 18 days Let the total work be 90 units Efficiency of βPβ = 90/15 = 6 units/day Efficiency of βQβ = 90/18 = 5 units/day Work done by βPβ and βQβ in 6 days = (6 + 5) Γ 6 = 66 units Therefore, x = (90 β 66)/6 = 24/6 = 4 days
? = (597.98 Γ· (6.97 2.01 β 3.1)) Γ 12.9
1153, 1206, ?, 1326, 1393, 1464
What is the least number of square tiles required to pave the floor of a room 11 m 47 cm long and 6 m 82 cm broad?
Which of the following statements is true about LPP?Β Β Β Β Β Β Β
What is the value of 8 β 4 Γ 16 β 4?Β
If logβ(81) = 4/3, find x.
Calculate the percentage contribution of the South branch's total revenue to the company's total revenue over the three years (2021-2023).
115, 138, 163, 190, 219, ?
A man drives at a steady speed of 75 km/h for 4 hours, followed by another stretch of 3 hours at a consistent speed of 40 km/h. What is his average spee...
A companyβs quarterly sales (in lakh units) are:
Q1: 18, Q2: 24, Q3: 21, Q4: 27
Find the percentage increase from...