Question

‘P’ is 20% more efficient than ‘Q’. ‘P’ can do a piece of work in 15 days. They begin the work together, but ‘Q’ leaves after 6 days. The rest of the work is completed by ‘P’ in ‘x’ days. What is the value of ‘x’?

A 2 days
B 13 days
C 8 days
D 6 days
E None of these