Question
βPβ is 20% more efficient than βQβ. βPβ can
do a piece of work in 15 days. They begin the work together, but βQβ leaves after 6 days. The rest of the work is completed by βPβ in βxβ days. What is the value of βxβ?Solution
ATQ, Time taken by βQβ to complete the work = 1.2 Γ 15 = 18 days Let the total work be 90 units Efficiency of βPβ = 90/15 = 6 units/day Efficiency of βQβ = 90/18 = 5 units/day Work done by βPβ and βQβ in 6 days = (6 + 5) Γ 6 = 66 units Therefore, x = (90 β 66)/6 = 24/6 = 4 days
Kolkata-based filmmaker Abu Sohel Khondekar's short film "Mehroon" won a special jury mention at which film festival?
Recently one of the following was in news because it got the Abel prize for the year 2022. Which option is correct?
Who partnered with the State Bank of India (SBI) for the 'Grow with the Trees' drive in Srinagar?
Which Indian Navy ship, commissioned in Russia, marks the last foreign-built warship in its fleet?Β
Recently Nikos Christodoulides was elected as the new President of which of the following country?
Who has been appointed as the new Chairman and Managing Director of Bharat Electronics Limited (BEL)?
INS Shivalik is set to participate in the Rim of the Pacific (RIMPAC) exercise. Where will this exercise be conducted?
What is the target year for the prototype launch of India's Advanced Medium Combat Aircraft (AMCA)?
What mission has the Council of Scientific and Industrial Research (CSIR) launched to enhance farmers' income by using smart agro-technologies?
Recently IDS has unveiled the Bharat Blockchain Network and Polyversity . IDS is based in which country?