Question
A and B together can complete a piece of work in 12
days, while B and C together can complete the same work in 15 days. A and C together can complete the work in 20 days. If all three work together, in how many days will they complete the work?Solution
Let the total work be the LCM of 12, 15, and 20, which is 60 units. Work rate of A and B together = 60 / 12 = 5 units/day. Work rate of B and C together = 60 / 15 = 4 units/day. Work rate of A and C together = 60 / 20 = 3 units/day. Adding all three equations: (A + B) + (B + C) + (A + C) = 5 + 4 + 3 = 12 units/day. Twice the combined work rate of all three (A + B + C) = 12. Work rate of A + B + C = 12 / 2 = 6 units/day. Time taken to complete the work = Total work / Combined rate = 60 / 6 = 10 days. Correct answer: a) 10
Competition Commission of India fined MakeMyTrip and Oyo for anti-competitive conduct in_____.
Name the person who presented the scheme to link Indian rivers by constructing a chain of canals in 1974.
Against which team did Sachin Tendulkar make his 100th international century?
First session of INC was held in which city?
Which one of the following statements is not correct?
Schedule commercial bank status is not given to?
Bond prices in the market decrease when the banks offer higher interest rates because-
What characteristic of invasive weeds contributes most to their threat in agricultural settings?
Minimum support price was applied on the recommendation of _____.
Which of the following compounds act/s as buffering agents in soil?
1. Carbonates
2. Phosphates
3. Arsenates