Question
Pawan can finish a task in 28
days, while Bhavna requires 7 more days than Pawan to complete the same task. They both started working together but stopped after 10 days. Raja then completed the remaining work in 5 days. Determine how long Raja alone would take to complete the entire task.Solution
ATQ,
Time taken by 'Bhavna' to complete the work = 28 + 7 = 35 days Let the total work be 140 units (LCM of 28 and 35) Efficiency of 'Pawan' = (140/28) = 5 units/day Efficiency of 'Bhavna' = (140/35) = 4 units/day Work completed by 'Pawan' and 'Bhavna' in 10 days = (5 + 4) × 10 = 90 units Remaining work = 140 - 90 = 50 units So, efficiency of 'Raja' = 50/5 = 10 units/day Therefore, time taken by 'C' to complete the entire work = 140/10 = 14 days
Answer the questions based on the information given below.
There are eight family members L, M, N, O, P, Q, R and S having two married couples ...
Answer the questions based on the information given below.
There are nine persons P, Q, R, S, T, U, V, W and Y are in a family of three generat...
Dharun has a brother Anand. Dharun is the son of Kumar. Krishnan is Kumar's father. How is Anand related to Krishnan?
How is W related to S?
How is B related to C?
How is L related to K?
Answer the questions based on the information given below:
If A% means A is a male, B($) means B is a female.
A @ B means A and B are si...
In the question, assuming the given statements to be true, find which of the conclusion (s) among given two conclusions is /are definitely true and the...
Who is the maternal uncle of K?
There are seven members (R, S, T, U, W, Y and V) in a family. V is the daughter of T’s brother. Y is the father of R. W is the mother of Y. U is fathe...