    A can complete a piece of work in 21 days. A starts the

    work alone. After 9 days, B joins A, and together they complete the remaining work in 5 days. Find the ratio of their efficiencies.
    A 2:5 Correct Answer Incorrect Answer
    B 5:7 Correct Answer Incorrect Answer
    C 4:3 Correct Answer Incorrect Answer
    D 7:2 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, A rate = 1/21 A work in 9 days = 9/21 = 3/7 Remaining work = 1 - 3/7 = 4/7 (A + B) rate = (4/7) / 5 = 4/35 B rate = 4/35 - 1/21 = 1/15 Efficiency ratio (A : B) = (1/21) : (1/15) = 15 : 21 = 5 : 7