Question
A can complete a piece of work in 18 days. B can
complete the same work in 72 days. While C is 33(1/3)Â more efficient than B. All three started working together. A left 8 days before the work was completed, and C left 17 days before but B continued to work till the end, for how many days did A work?Solution
Given C is 33.33% is more efficient than B. But A left before 8 days = 18-8 = 10 Days So A worked only 10 Days.
Choose a figure which would most closely resemble the unfolded form of figure (Z).
Select the figure which will come next in the following figure series.
Select the figure that can replace the question mark (?) in the following series.
Which figure is different from the rest?

A piece of paper is folded and cut as shown below in the question figures from the given answer figures, indicates how it will appear when opened?
<...How many triangles are there in the given figure?

Three of the following four figure pairs are alike in a certain way and thus form a group. Which is the one that does not belong to that group?
<...
Select a figure from amongst the Answer Figures.
...Â
How Many Triangles are there in the given figure?
