Question
35 men can complete a piece of work in 40 days. ‘x’
men started the work and after 30 days 60 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’Solution
Total work = 35 × 40 = 1400 units According to question; 30 × x + 10 × (x + 60) = 1400 Or, 30x + 10x + 600 = 1400 Or, 40x = 800 Or, x = 20
In which year did the World Health Organization (WHO) declare the surge of Mpox (Monkeypox) cases a Public Health Emergency of International Concern (PH...
Who honored with “Pravasi Bhartiya Samman” award 2023 ?
What is the designated brand name for India's premium Cotton in the world cotton trade, representing Whiteness, Brightness, Softness, Purity, Luster, Un...
What is the significance of the new plant species Emblica chakrabartyi discovered in Kerala?
What is the significance of the National Council of Educational Research and Training (NCERT) being granted the deemed-to-be-university status?
What was the primary method used by researchers to confirm the lunar cave?
Which major port recorded an 8% year-on-year growth in cargo volume in 2024-25?
What is the maximum Central assistance provided for sewerage projects under AMRUT for cities with a population less than 1 lakh?
Which real estate developer was awarded as the "Emerging Developer of the Year"?
What is the primary capability of the AKASH-NG missile system?