📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Month End Offer - Flat 52% Off On All Courses! Enroll Now âš¡
    00:00:00 AM Left

    Question

    X and Y together can complete 30% of a work in 12 days

    while Y alone takes 100% more time than X and Y together to finish the whole work. Find the time taken by X alone to complete 50% of the whole work.
    A 75 days Correct Answer Incorrect Answer
    B 40 days Correct Answer Incorrect Answer
    C 90 days Correct Answer Incorrect Answer
    D 85 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Time taken by X and Y together to complete the whole work = 12/0.30 = 40 days Time taken by Y alone to complete the whole work = 2.00 × 40 = 80 days Total work = 240 units (LCM of 40 and 80) Amount of work done by X and Y together in one day = 240/40 = 6 units Amount of work done by Y alone in one day = 240/80 = 3 units Amount of work done by X alone in one day = 6 – 3 = 3 units Desired time = (0.50 × 240)/3 = 40 days

    Practice Next

    Relevant for Exams:

    ask-question