Question
Rahul can complete a project in 50 days, while Karan can
finish the same project in 75 days. Rahul starts working alone, and after 30 days, Karan joins him. How many additional days will Rahul and Karan take together to finish the remaining work?Solution
ATQ; Let the total work = 150 units (LCM of 50 and 75) Rahul’s efficiency = 150/50 = 3 units per day Karan’s efficiency = 150/75 = 2 units per day Work done by Rahul in 30 days = 30 × 3 = 90 units Remaining work = 150 – 90 = 60 units Work done by Rahul and Karan together = 60/(3+2) = 60/5 = 12 days
As per the provisions of the Maternity Benefit Act, 1961, the maximum period for which a female employee shall be entitled to leave with wages as mater...
As per the Status of Tigers, 2022 Report released in April 2023, what percentage of the total world wild tiger population does India account for?
Which of the following festival is celebrated in Odisha?
India’s proposed manned mission to space by ISRO is named as
In the 1907 session of the Indian National Congress, did the Congress split into two parties, soft parties and hot parties?
Which authority should an Indian Citizen approach for securing his fundamental right of personal freedom guaranteed by the Constitution?
Who won the gold medal in the Javelin Throw event at the World Para Athletics Championships 2023?
 The STARS( Scheme for Translational and Advanced Research in Science) according to the National Education Policy will provide _______ crore funding/su...
Padma awardee Arjun Singh Dhurve is related to which of the following folk dances?
In which among the following states is the Vindhyachal Super Thermal Power Station located?