Question
A certain Sales target was assigned to a team of men to
complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sales target in 30 days. What was the original number of men in the team?Solution
ATQ, we can say that Let the original no. of men in the team be taken as = ‘x’ then, 18x = 30(x - 8) 12x = 240 x = 20 men
What does "fixed term employment" mean according to the Code on Social Security?
Under the Companies Act, 1956, what is the relationship between the Memorandum of Association and the Articles of Association?
Under the Indian Evidence Act, what is required when a place liable to search under a warrant is closed?
“The Commission may call for reports, returns and statements from the Central Government or corporations established by any Central Act.”
Thi...
Under the RTI Act, an appeal shall be disposed of within __________days of the receipt of the appeal or within such extended period not exceeding a tota...
A Vigilance Commissioner is convicted for an offence which, in the opinion of the Central Government, involves moral turpitude. What is the legal positi...
Under Section 107, abetment of suicide of which of the following persons can lead to punishment with death?
A notification under Section 3 of the DSPE Act specifies that certain offences under a Central Act shall be investigated by the Delhi Special Police Est...
Under Order 21 of the Code of Civil Procedure, 1908 (Execution), the court can issue a decree for:
If irrelevant evidence is so mixed up with relevant evidence as to make it impossible to separate one from the other then.