Question
A certain Sales target was assigned to a team of men to complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sales target in 30 days. What was the original number of men in the team?
More Time and work Questions
- A and B can do a piece of work in 12 days and 18 days, respectively. They start working together, and after 4 days, A leaves the work. How many more days w...
- David can complete a work alone in 30 days, while Ethan can complete the same work in 50 days. Both of them started the work together and worked till 96% o...
- A, B, and C can together complete a task in 12 days. A and B can complete the same task in 16 days, and B and C can complete it in 20 days. In how many day...
- 45 engineers working 5 hours a day take 15 days to complete a project. How many engineers working for 4 hours a day are needed to complete three times the ...
- A can do a job alone in 66 days, B can do it alone in 55 days, while A, B, and C working together can complete the job in 11 days. In how many days can C d...
- A alone can complete a work in 15 days. He works alone for 6 days, then B joins him and together they finish the remaining work in 4 more days. In how many...
- A is twice as efficient as B. Together they can complete a work in 18 days. In how many days can A alone complete the work?
- Ananya and Riya can complete a task in 20 hours and 40 hours respectively. Ananya works alone for 10 hours and then Riya finishes the remaining task. How l...
- A, B, and C together can do a piece of work in 28 days, whereas C alone can do the same work in 42 days. How long will A and B take together to finish it?
- ‘A’ alone can complete a work in 17 days. ‘B’ alone can complete the same work in 34 days. If ‘A’ and ‘B’ work together for 5 days, then the remaining work...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)