Question
A can do a piece of work in 21 days and B in 28 days. If they together work on it for 5 days, then the fraction of the work that is left is :
More Time and work Questions
- A man is thrice as fast as a women and a woman is twice as fast as a boy. If all of them can do a work in 18 days. than a boy can do the work in?
- Amit and Ankit can complete a job in 60 days. Working together with Sumit, they can finish it in 40 days. How many days would Sumit alone take to complete ...
- A contractor is hired to complete a road in 40 days and initially employs 40 workers. After 24 days, he realizes that only one-third of the work has been c...
- Aisha and Neel can complete a job alone in 66 days and 99 days respectively. Working together, they earn a total wage of Rs. 11,550. How much does Aisha re...
- Ravi can complete a task alone in 12 days. After a few days, Mohan joins him and both complete the remaining 50% of the work in 3 days. How long will Mohan...
- ‘A’ is 20% more efficient than ‘B’. ‘A’ and ‘B’ work together for 6 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 6 more days to finis...
- Mukta takes 8 hours less than Raj to complete the work, and Mukta also takes 32 hours less than Bheem to complete the same work. If Raj and Bheem start wor...
- Anil alone can finish some work in 50 days. Anil and Aman completed the work together and earned Rs. 9,000 as wage. If Aman's wage share is Rs. 3,600, then...
- A man, a woman and a boy can do a work in 3, 2, 6 days respectively. How many children were required with 1 man and 1 woman to complete the same work in 1/...
- 20 men can finish a work in 220 days, but at the end of 90 days, 20 additional men are employed. In how many more days will the work be completed?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt