Question

A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?

A 5(5/11) days
B 5(5/6) days
C 6 days
D 8(3/4) days
E 7(1/5) days