Question
Team A can built a project in 6 hours less than the time
taken by Team B to built the same project. The ratio of the strength of Team A to that of Team B is ______. If it is given that the efficiencies of each member of both the teams is same (where the efficiency is measured in work done per hour), then which of the following ratios will satisfy the condition? (i) 9:6Â Â (ii) 22:38Â Â (iii) 17:12Â Â (iv) 15:23Solution
Since Team A is taking less time than Team B and each member has the same efficiency. With this we can say that the strength of Team A will be greater than that of Team B. Thus only (i) and (iii) satisfy the condition (first term is greater than that of second term). Alternative Method:               Team A   Team B Time:            T       T+6 Strength:          A        B Work Done:       AT   =   B(T+6) ؞ Then, AT = B(T+6) A/B = (T+6)/T Thus, we can say that A > B. Hence only option (i) and (iii) satisfy the condition.
Which of the following is true regarding the Reserve Bank of India's prudential norms for income recognition, asset classification, and provisioning for...
A Micro or Small Enterprise may be said to have become Sick, if any of the borrowal account of the enterprise remains NPA for ________ months or more.
Which of the following statements accurately describe payday loans?
1) Payday loans are typically repaid in a single payment on the borrower's ne...
Which of the following formulae correctly calculates the Operating Profit Margin?
Which of the following is considered an intangible asset?
Which of the following is NOT a use of ATM cards?
With project cost of Rs.300 lakh and cost of capital at 12%, the estimated profits over its lifetime of 5 years are Rs.10 lakh, Rs.10 lakh, Rs.30 lakh, ...
Which of the following RBI directions provides the legal authority for the issuance of the Master Direction on KYC?
What is the primary goal of implementing expansionary fiscal policy during a recession?
Where is personal wealth management more skewed towards?