Question
Ratio of the work done by P, Q and R in one day is 6:4:7 respectively. They all together can complete the work in 45 days. Q and R worked on it for 27 days. In how many days P will complete the remaining work.
More Time and work Questions
- Sufficient food-supply was arranged to last for 30 days for 250 soldiers. If 50 soldiers did not attend the camp, for how many extra days will the food-sup...
- 30 typists working 7 hours per day can complete a typing job in 15 days. ____ typists working _____ hours per day can complete (2/3)rd part of the work in ...
- ‘P’ can complete a project in 12 days. ‘Q’ is 40% less efficient than ‘P’. Working together, ‘P’, ‘Q’ and ‘R’ can finish the job in 5 days. In how many day...
- A and B together can do a piece of work in 15 days which B and C together can do in 20 days. After A has been working at it for 3 days and then by B for 11...
- ‘A’ and ‘B’ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after ‘x’ days ‘A’ left the work and the r...
- A person can make 48 flower pots in an hour. Working for 3 hours daily, he has total 660 flower pots that to be made in 4 days time. To accomplish this wor...
- Ajay alone can complete a work in 50 days. Vijay is four times as efficient as Ajay. Find the percentage of work completed by Ajay and Vijay together in 10...
- 'A' alone can do some work in 24 days, 'B' alone can do the same work in 48 days. If they work on alternate days, starting with 'B', then the work will be ...
- ‘R’ and ‘S’ can do a piece of work in 20 days and 30 days, respectively. ‘R’ started working alone and was replaced by ‘S’ after 10 days. In how many days ...
- A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2(1/...