Question
15 men can finish a job in 24 days, while 36 women can do
the same job in 20 days. How long will 1 man and 1 woman take to complete the work together?Solution
ATQ,
Let the efficiency of a man and a woman be 'M' and 'W' units/day, respectively.
So,15 × 24 × M = 36 × 20 × W
Or, M:W = 720 : 720 = 5 : 3
Let M = 5e and W = 3e
Let the required time be 'T' days
So, (5e + 3e) × T = 15 × 24 × 5e
Or,8T = 1800
∴ T = 1800 ÷ 8 = 225 days
Consider the following statements regarding Section 66B (Dishonestly Receiving Stolen Computer Resources) of the IT Act, 2000:
Statement 1: A ...
Consider the following statements regarding the prohibition on the use of company name under Section 5 of the Companies Act, 2013:
Statement 1...
An intentional false communication either published or publicly spoken, that injures another reputation among other people in society is known as ______...
What role does the Central Government have in relation to public awareness about pollution control?
A, on his trial before the Court of Session, says that a deposition was improperly taken by B, who is the Magistrate, in such a case:
Section dealing with “Related Party Transactions”:
Consider the following statements regarding abetment of PCA offences under Section 12 of PCA, 1988:
Statement 1: Abetment of public servant's cor...
As per the IBC Insolvency Commencement date means_________
The "Principle of Natural Justice" requires that:
Which of the following is correct relating to the licensing of the banking companies?