Question
90 men can complete a work in 32 days. Eight days after
they started working, 72 more men joined them. How many days will they now complete the remaining work ?Solution
From: M1D1/W2 = M2D2/W1 90 × 32 = (90 × 8) + (90 + 72) × D2 D2 = 3 days (approx.)
Which countries are involved in the agreement for Quick Impact Projects (QIPs) signed between India and Nicaragua?
Where was the first International Dairy Federation Asia-Pacific Summit held?
Regarding the Ayushman Bharat, consider the following statements:
1.It offers a sum insured of 5 lakh per family for secondary and tertiary care....
Which of the following Indian literary works was not included in UNESCO’s Memory of the World Register?
India's first booster vaccine, GEMCOVAC-OM, is designed to target which COVID-19 variant?
Consider the following statements with respect to ‘Local self-government’:
1. In 1687, Bombay achieved the distinction of being the fir...
In which country was India's first overseas Jan Aushadhi Kendra inaugurated in July 2024?
International Nelson Mandela Day is observed on
Which of the following bank has recently launched “Parivar” (family) savings account in FY24?
Who became the 1st Indian to win the first-ever medal at the Asian fencing championships held in Wuxi, China?