90 men can complete a work in 32 days. Eight days after
they started working, 72 more men joined them. How many days will they now complete the remaining work ?Solution
From: M1D1/W2 = M2D2/W1 90 × 32 = (90 × 8) + (90 + 72) × D2 D2 = 3 days (approx.)
What does the term "product" include according to the definition provided "under the Consumer Protection Act" ?
Under the Right to Information (RTI) Act, 2005, information cannot be denied if:
Which scheme is employed by manufacturers who need ISI mark (BIS standard mark) within 30 days as per the government notification?
The President
In case of 3 arbitrators appointment of presiding arbitrator can be made by____.
Within what time frame must the Central Government constitute the Board of Approval after commencement of the SEZ Act?
The Court may presume that a document which is _____ old is genuine.
APEDA & MPEDA comes under the ambit of which ministry
What is the punishment for providing false evidence under the Companies Act?
For the purpose of section 363-A of Indian Penal Code, 1860, 'Minor' means:-