Question
90 men can complete a work in 32 days. Eight days after
they started working, 72 more men joined them. How many days will they now complete the remaining work ?Solution
From: M1D1/W2 = M2D2/W1 90 × 32 = (90 × 8) + (90 + 72) × D2 D2 = 3 days (approx.)
What is the name given to the difference between value of output and value added?
Which of the following transaction is being ignored while calculating national income?
Due to which of the following reasons increase in absolute and per capita real GNP do not connote a higher level of economic development?
Which one statement is correct among the given below?
A shift of the supply curve of oil raises the price from $10 a barrel to $15 a barrel and reduces the quantity demanded from 40 million to 15 million ba...
Which of the following is not a method to calculate GDP?
In India what is the current base year being used for the calculation of GDP?
Which of the following methods is used to control inflation in India?
Which one of the following transactions will be considered as a transfer payment?
Which of the following statement is correct about the situation in the economy?