Question
5 girls can do a piece of work in 9 days, 4 boys can do
the same piece of work in 8 days, 6 men do the same piece of work in 2 days and 4 women can do the same piece of work in 4 days. Who is least efficient?Solution
5 girls can do a piece of work = 9 days 1 girl can do a piece of work = 9 × 5 = 45 days. 4 boys can do a piece of work = 8 days 1 boy can do a piece of work = 4 × 8 = 32 days. 6 men can do a piece of work = 2 days 1 men can do a piece of work = 6 × 2 = 12 days. 4 women can do a piece of work = 4 days 1 woman can do a piece of work = 4 × 4 = 16 days. Hence, girls are least efficient.
Building ‘Lotus Mahal’ and 'Mahanavmi Dibba' was a notable feature in the kingdom of
Which of the following Congress Leader has a famous slogan ''Do or Die''?Â
With reference to the metal sculptures of Indus Valley Civilization, consider the following statements:
1. Sand-casting was the most prevalent te...
King Ajatashatru belonged to which dynasty?
'Who is called the father of Indian archaeology?
Which of the following personalities were the famous poetess of Indian Vedic age?
1. Lopamudra
2. Gargi
3. Gosha
4. Meera Ba...
‘Dibrugarh’ is situated on the bank on the river _________
Consider the following statements regarding iqta system:
1. Iqtas were administered by Muqtis.
2. Iqtas were made hereditary by Sultan Fir...
________ religion is related to Sannati.
The Indo Greeks were the first ruler in India who issued