Question
A, B and C can complete a piece of work in 5, 10 and 20 days respectively. They all start work together, but C leaves after 2 days. In how many total days is the work completed?
More Time and work Questions
- A alone can complete a work in 18 days, and B alone can complete the same work in 24 days. They start working together, but A leaves after 4 days. In how m...
- Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of ...
- 'Asmita,' who is three times as efficient as 'Bittu,' can complete a task on her own in 15 days. 'Asmita' and 'Bittu' began working together, but after 3 d...
- 'B' and 'N' can collectively finish a task in 88 days, and 'N' and 'S' together can complete the same work in 66 days. If 'B' and 'S' work together, they c...
- A and B can jointly finish a task in 42 days, while B and C together take 35 days to finish the same task. If B can finish the task alone in 105 days, how ...
- Work Efficiency of Raghav and Vaibhav are in the ratio of 12:14. Both of them worked together and finished the work in 9 days. In how many days, the total ...
- If 20 men or 12 boys can complete a job in 25 days, how long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate...
- Komal and Seema individually can complete a task in ‘4a’ hours and ‘6a’ hours respectively. If they together can complete half of the work in 6 hours, then...
- 'P', 'Q', and 'R' can individually complete a task in 20, 24, and 30 days, respectively. They all started working together, but 'P' stopped after 4 days. A...
- The time taken by ‘A’ to build a wall alone is 40% more than the time taken by him to build it along with ‘B’. ‘B’ will take how much percent more time to ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)