      Question

      A is twice as efficient as B. Together they can complete

      a work in 18 days. In how many days can A alone complete the work?
      A 21 days Correct Answer Incorrect Answer
      B 27 days Correct Answer Incorrect Answer
      C 17 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer

      Solution

      ATQ, Let B’s 1-day work = x Then A’s 1-day work = 2x Together: 3x = 1/18 x = 1/54 So A’s rate = 2x = 2/54 = 1/27 Hence A alone takes 27 days.