      P’s 2 days work is equal to Q’s 5 days work. If P

      and Q together can complete the work in 30 days then how much time Q will take to complete 60% of the work?
      A 60 days Correct Answer Incorrect Answer
      B 48 days Correct Answer Incorrect Answer
      C 63 days Correct Answer Incorrect Answer
      D 44 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Ratio of efficiency of P and Q = 5:2 Let the efficiency of P and Q be 5x and 2x units per day respectively. Total work = 7x × 30 = 210x units Required time = (0.60 × 210x)/2x = 63 days