πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    A and B can complete a task together in 26 days, while B

    alone takes 52 days to finish it. A began working alone and left after β€˜x’ days, after which B completed the remaining work in 39 days. Determine the percentage of the total work completed by A.
    A 25% Correct Answer Incorrect Answer
    B 15% Correct Answer Incorrect Answer
    C 20% Correct Answer Incorrect Answer
    D 40% Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let total amount of work be 52 units
    Efficiency of (A + B) = 52/26 = 2 units/day
    Efficiency of β€˜B’ = 52/52 = 1 unit/day
    Amount of work done by β€˜B’ = 39 Γ— 1 = 39 units
    Percentage of work done by β€˜A’ = {(52 – 39)/52} Γ— 100 = 25%

    Practice Next
    More Time and work Questions
    ask-question