Question
A and B can complete a task together in 12 days, while B
alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B completed the remaining work in 18 days. Determine the percentage of the total work completed by A.Solution
Let total amount of work be 16 units
Efficiency of (A + B) = 16/8 = 2 units/day
Efficiency of ‘B’ = 16/16 = 1 unit/day
Amount of work done by ‘B’ = 12 × 1 = 12 units
Percentage of work done by ‘A’ = {(16 – 12)/16} × 100 = 25%
The ‘Sort & Filter’ group is available under which of the following tabs in MS Excel 365?
What is the name of the viruses that fool a user into downloading and/or executing them by pretending to be useful applications?
Which boot process is also known as Bootstrapping?
Which database is commonly used with LibreOffice Writer?
Which of the following authentication methods is the most secure?
What is the primary goal of computer security?
Which key starts a slide show in PowerPoint?
Which of the following is not an antivirus software?
Which component is responsible for the visual output of a computer?
What type of system is supported by Linux?